It’s full steam ahead for stages 12 & 13

09/04/2014 - Development

Construction of 12a is essentially complete with only the grassing and streetlights to go, and this area will be accessible to both pedestrians and vehicles by mid April. 12a provides a mix of lot sizes and a strip of highly desirable lake front sections. Interest has been strong and there are limited lots left un sold from stage 12a.

Stage 13 is about two thirds of the way through construction, with all of the underground services in place. The road works for stage 13a will be complete around mid May;  and the road works for 13b will be complete around Mid August.

We are expecting to open the walking track around the northern wetlands and up into stage 13 this coming spring.